ASX gold & copper project updates, decoded

Price-sensitive announcements only - the ones that can move the share price - each decoded within minutes of release. 6 announcements so far.

Northern Star Resources Project update

KCGM October gold 15.3koz below plan, tracking lower end of 550-650koz; Hemi gets primary approvals

ASX: "Major Growth Projects Update"

Northern Star says the expanded KCGM plant performed variably in October, producing 15.3koz after a 3.5-day maintenance shutdown. KCGM is now tracking toward the lower end of its 550-650koz FY27 range, while group FY27 guidance...

Westgold Resources Project update

Beta Hunt hits 2Mtpa annualised rate in September; main ventilation fans not fully commissioned

ASX: "Beta Hunt Infrastructure Investment Enables 2Mtpa Run Rate"

Westgold says Beta Hunt's infrastructure upgrades, including a temporary ventilation system, supported an annualised mining rate of 2.0Mtpa in September 2026, and it targets sustained 2Mtpa from October to December 2026. The main...

Regis Resources Project update

Court rules McPhillamys Section 10 declaration invalid; minister to redetermine application

ASX: "Federal Court Rules McPhillamys s10 Declaration Invalid"

On 14 October 2026 Regis said the Federal Court found the Section 10 Declaration over part of the McPhillamys site to be legally invalid. The Environment Minister is expected to redetermine the application, but no timeline is...

Capricorn Metals Project update

Karlawinda Expansion completed on schedule; 6.5Mtpa throughput reached, about 150koz a year expected

ASX: "Karlawinda Expansion Project Completed on Schedule"

Capricorn says the Karlawinda Expansion Project is built and has started continuous ore processing, with the plant at its targeted steady state throughput of 6.5Mtpa. The plant is still treating low grade ore and product size is...

Evolution Mining Project update

Evolution project briefing: no new drilling or resources; project timelines and growth targets

ASX: "Current projects and future growth opportunities"

Evolution's 15 September 2026 investor briefing updates project status and timing at Cowal, Northparkes and Ernest Henry. It reports no new drill results and no new resource or reserve estimate; the resource and reserve tables...

Greatland Resources Project update

Greatland gets WA environmental approval for Havieron, completing both state and federal primary approvals

ASX: "Havieron Environmental Approvals Received"

Greatland says the WA Minister for the Environment has given the state primary approval for its Havieron gold-copper project, following the federal approval of 24 April 2026. With both primary approvals in hand, the company is...

General information only - not financial advice. DrillScore's analyses are produced automatically by an AI model (Claude, by Anthropic) from the company's own ASX announcement and public market data, and scored by a fixed formula (how it works). They can be wrong or incomplete, don't consider your objectives or circumstances, and are not a recommendation to buy, sell or hold anything. Always read the original announcement and consider advice from a licensed adviser.

Give the next investor an edge

Don't invest blind.

The headline is the company's story. Your experience is the rest of it. Share what you learned from a gold or copper stock - two minutes, anonymous, and it helps everyone who comes after you.

Share your experience See the latest decoded